Detour Information

Phase 1 – February 2020 thru August 2021

Phase 2 – August 2021 to January 2022

Phase 3 – January 2022 to March 2022

Phase 4 – March 2020 thru June 2020

Phase 5 – December 2019 thru October 2020

Phase 6 – October 2020 thru May 2021

Phase 7 – May 2021 thru June 2021

Phase 1

Status: Active 

Duration: February 2020 thru August 2021 

Location: SR 141 from Jay Drive to Airport Road 

Closures/Restrictions

  • SR 141 reduced to a single lane in each direction from Jay Drive to just south of Commons Boulevard  
  • Intermittent nightly lane closures on northbound and southbound SR 141 for pavement rehabilitation from US 13 to Jay Drive 
  • Paul Road closed for reconstruction  

Phase 1A

Status: Not started 

Duration: One weekend (TBD) in March 2021 

Location: SR 141 and Commons Boulevard intersection 

Closures/Restrictions

  • Southbound SR 141 closed at Commons Boulevard. Southbound SR 141 motorists must turn right onto westbound Commons Boulevard  
  • Eastbound Commons Boulevard closed at Spruance Drive  
  • No left turn from Northbound SR 141 onto westbound Commons Boulevard  
  • Westbound Commons Boulevard through and left turn closed. Westbound Commons Boulevard must turn right onto northbound SR 141 

Detour Information:  

  • For traffic normally accessing southbound SR 141 
    • Detoured to Ramp E to northbound I-295 to southbound US Route 13 to access southbound SR 141. 
  • For traffic normally accessing Commons Boulevard from the south and east
    • Detoured along northbound SR 141 to Ramp L to Ramp K to southbound SR 141 to access Commons Boulevard. 
  • For traffic normally utilizing the eastbound Commons Boulevard approach at SR 141
    • Detoured to eastbound SR 58 to eastbound SR 273 to northbound US Route 13 to access SR 141. 

Phase 1B

Status: Not started 

Duration: One weekend (TBD) in March 2021 

Location: SR 141 and Commons Boulevard intersection 

Closures/Restrictions

  • Northbound SR 141 closed at Commons Boulevard. Northbound SR 141 motorists must turn left or right onto Commons Boulevard   
  • Westbound Commons Boulevard through and left turn lanes reduced to a single lane  
  • Southbound SR 141 left turn closed onto eastbound Commons Boulevard 

Detour Information:  

  • For the detour route located prior to the closure 
    • Detoured to northbound US Route 13 to southbound I-295 to Ramp N to access northbound SR 141.
  • For the detour route located after the closure
    • Detoured to westbound Commons Boulevard to westbound SR 58 to northbound I-95 to Ramp D-2 to access northbound SR 141   

Phase 1C

Status: Not started 

Duration: One weekend (TBD) in April 2021 

Location: SR 141 and Commons Boulevard intersection 

Closures/Restrictions

  • Northbound SR 141 closed between Bellecor Drive and Commons Boulevard 
  • Left turns from Eastbound Commons Boulevard onto northbound SR 141 reduced to a single lane  
  • Westbound Commons Boulevard left, through, and right turn lanes reduced to a single lane 

Detour Information:  

  • For vehicles trying to access Commons Boulevard from northbound SR 141
    • Detoured to southbound US Route 13 to westbound SR 273 to westbound SR 58 to eastbound Airport Road to access Commons Boulevard. 
  • For vehicles traveling to northbound SR 141
    • Detoured to northbound US Route 13 to southbound I-295 to ramp to access northbound SR 141. 

Phase 1 – NB SR 141 Stage 2 

Status: Not started 

Duration: September 2020 thru March 2020 

Location: Northbound SR 141 from Commons Boulevard to Airport Road 

Closures/Restrictions: None 

Back to the top

Phase 1 – SB SR 141 Weekend 

Status: Not started 

Duration: One weekend (TBD) in April 2021 

Location: Southbound SR 141 from Creekwood Crossover to Commons Boulevard 

Closures/Restrictions: Southbound SR 141 reduced to a single lane 

Back to the top

Phase 1 – NB SR 141 Weekend 

Status: Not started 

Duration: One weekend (TBD) in in April 2021 

Location: Northbound SR 141 from Commons Boulevard to Airport Road 

Closures/Restrictions: Northbound SR 141 reduced to a single lane 

Back to the top

Phase 1 – Commons Boulevard West Stage 1 

Status: Not started 

Duration: June 2020 to August 2020 

Location: West leg of Commons Boulevard 

Closures/Restrictions: None 

Back to the top

Phase 1 – Commons Boulevard West Stage 2 

Status: Not started 

Duration: March 2021 to April 2021 

Location: West leg of Commons Boulevard 

Closures/Restrictions: None 

Back to the top

Phase 2 

Status: Not started 

Duration: August 2021 to January 2022 

Location: SR 141 from Jay Drive to Airport Road 

Closures/Restrictions

  • SR 141 reduced to a single lane in each direction from Jay Drive to just south of Commons Boulevard
  • Southbound SR 141 left turn onto Bellecor Drive closed 

Phase 3 

Status: Not started 

Duration: January 2022 to March 2022 

Location

  • Island and median work in SR 141 and Commons Boulevard intersection 
  • Island work at commercial entrances along northbound SR 141  
  • Asphalt paving from Jay Drive to Airport Road, and Commons Boulevard 

Description: Reconstruct islands and medians, place top course of asphalt pavement, install pavement striping and signs 

Closures/Restrictions: Occasional SR 141 and Commons Boulevard lane closures to complete island and median work, nightly lane closures for pavement 

Back to the top

Phase 4 – Stage 1 Airport Road 

Status: Completed

Duration: March 2020 thru April 2020 

Location: Reconstruct Ramp E (ramp from southbound SR 141 to northbound I-295) and westbound Airport Road  

Closures/Restrictions: Ramp E and westbound Airport Road closed  

Detour Information:  

  • For traffic normally utilizing Ramp E, there will be two detour routes with one route located prior to Ramp E and the other detour located after Ramp E. 
    • The detour route before Ramp E will have vehicles detour to southbound I-95 to westbound SR 58 to southbound SR 7 to northbound I-95 to access northbound I-295.  
    • The detour route after Ramp E will have vehicles continue along southbound SR 141 to northbound US Route 13 to access northbound I-295.
  • For traffic normally utilizing westbound Airport Road
    • Detour route will have vehicles continue south along SR 141 to westbound Commons Boulevard to access Airport Road. 

Phase 4 – Stage 2 Airport Road 

Status: Completed

Duration: May 2020 thru June 2020 

Location: Reconstruct Airport Road  

Closures/Restrictions: Eastbound Airport Road closed  

Detour Information:  

  • For traffic normally utilizing eastbound Airport Road
    • Detour route will have vehicles continue south along Airport Road to eastbound SR 58 to eastbound SR 273 to northbound US Route 13 to access southbound SR 141.   

Phase 5

Status: Completed

Duration: December 2019 thru October 2020 

Location: SR 141 from Airport Road to Newport, Southbound I-95 

Closures/Restrictions: Temporary signals on SR 141 at on-ramps 

Back to the top

Phase 5A

Status: Completed 

Duration: September 2019 thru October 2019 

Location: Ramp H (ramp from southbound SR 141 onto southbound I-95), Ramp K (ramp from southbound I-95 onto southbound SR 141) 

Closures/Restrictions: Ramps closed 

Phase 5B

Status: Completed 

Duration: November 2019 thru December 2019 

Location: Ramp L (ramp from northbound SR 141 onto southbound I-95), Ramp M (ramp from southbound I-95 to northbound SR 141) 

Closures/Restrictions: Ramps closed 

Phase 5C

Status:  Completed

Duration: Weekends thru September and October 2020 

Location: Ramp G (Southbound SR 141 ramp onto northbound I-95) 

Closures/Restrictions: Ramp closed 

Detour Information:  

  • For traffic normally utilizing Ramp G (Ramp from Southbound SR 141 to northbound I-95)
    • Detour route will have vehicles continue south along SR 141 to northbound US 13 to southbound I-295 to access either northbound I-95 or northbound I-495. 

Phase 5 Strip

Status: Completed

Duration: April 1, 2020 thru April 15, 2020 

Location: Southbound SR 141 from I-95 to Newport 

Closures/Restrictions:  Southbound SR 141 reduced to one lane between Newport on-ramp and exit to southbound I-95. Ramp closed from SR 4  onto southbound SR 141.

Detour Information:  

  • For traffic normally utilizing the ramp from SR 4 to southbound SR 141
    • Detour route will have vehicles continue south along eastbound Delaware Route 4 (Market Street), to Marshall Street, ramp to James Street, continue to Newport Gap Pike, to Boxwood Road to Newport Gap Pike, to ramp to southbound SR 141. SR 141 to northbound US 13 to southbound I-295 to access either northbound I-95 or northbound I-495. 

Back to the top

Phase 5D

Status: Not started 

Duration: Weekends thru October and November 2020

Location: SB SR 141 from Newport to Ramp H (Ramp from southbound SR 141 to southbound I-95), NB SR 141 from Ramp L (ramp from northbound SR 141 to southbound I-95 ramp) to Newport

Closures/Restrictions: SR 141 reduced to a single lane and ramp closures 

Detour Information:  

  • Ramp from SR 4 to SB SR 141
    • Continue south along eastbound (EB) Delaware Route 4 (Market Street), to Marshall Street, ramp to James Street, continue to Newport Gap Pike, to Boxwood Road to Newport Gap Pike, to ramp to SB SR 141. SR 141 to NB US 13 to SB I-295 to access either NB I-95 or NB I-495.
  • Ramp N
    • After Ramp N – travel along SB I-95 to exit to westbound (WB) SR 58 to SB SR 7 to NB I-95 to access NB SR 141.
    • Prior to Ramp N – exit from SB I-295 to SB US Route 13 to access NB SR 141.
  • Ramp L (NB SR 141 to SB I-95)
    • Take the ramp to Delaware Route 4, continue straight onto Marshall Street, turn left onto westbound Delaware Route 4 (Justis Street), turn left onto James Street, turn left onto EB Delaware Route 4 (Market Street), take the ramp to SB SR 141, and take the ramp to SB I-95.
  • Ramp M
    • After Ramp M – take the ramp to Delaware Route 58 (Churchmans Road), turn right onto WB Delaware Route 58 (Churchmans Road), turn right onto NB Delaware Route 7 (Stanton Christiana Road), continue straight onto EB Delaware Route 4 (Mitch Road/Market Street), turn left onto Marshall Street, take ramp to NB SR 141.
    • Prior to Ramp M – take the ramp to NB I-295, take the ramp to NB US 13, take ramp to SB US 13, turn left onto SB US 13, and take the ramp to NB SR 141.

Phase 5 – Bridge Construction

Status:  Completed

Duration: December 2019 thru October 2020 

Location: SR 141 over southbound I-95 

Closures/Restrictions: Occasional southbound I-95 lane and ramp closures 

Phase 6

Status:  Active

Duration:  October 2020 thru May 2021 

Location: SR 141 from Airport Road to Newport, Southbound I-95 

Closures/Restrictions: Temporary signal on Ramp K (southbound I95 ramp onto southbound SR 141) 

Back to the top

Phase 6 – Bridge Construction 

Status: Active

Duration:  October 2020 thru May 2021 

Location: SR 141 over southbound I-95 

Closures/Restrictions: Occasional southbound I-95 lane and ramp closures 

Phase 6A 

Status: Active

Duration:  October 2020 to December 2020 

Location: Ramp N (ramp from southbound I-295 onto northbound SR 141) 

Closures/Restrictions: Ramp closure 

Detour Information:  

  • For traffic normally utilizing Ramp N there will be two detour routes with one route located prior to Ramp N and the other located after Ramp N. 
    • The detour route located after Ramp N will instruct drivers to travel along southbound I-95 to exit to westbound SR 58 to southbound SR 7 to northbound I-95 to access northbound SR 141.  
    • The detour route located prior to Ramp N will have drivers exit from southbound I-295 to southbound US Route 13 to access northbound SR 141.  

Phase 7 

Status: Not started 

Duration: May 2021 thru June 2021 

Location: SR 141 from Airport Rd to Newport, southbound I-95, Southbound I295, Airport Road 

Description: Place top course of asphalt pavement, install pavement striping and signs Closures/Restrictions: Nightly lane closures